Command center for vendors, factories, production, quality, and shipping. Manufacturing time is infrastructure time.
Active Project
Factory: Daisy – China · Sample StageCurrent Stage
Sample Stage
Brain · Body · Energy Code
Production Progress
7%
Sample Status
Ships air Jun 25 → Jul 9
Production Status
Starts Jul 13 (post deposit)
Shipping Status
Vessel Aug 3–5
Expected Arrival
Aug 28 – Sep 9
Sea + customs + trucking
Factory Contact
Daisy Chen
+86 138 0000 0000
daisy@gd-comehealth.com
Last Factory Update
2026-06-15
All three formulas filled into stick packs. Photos to come tomorrow.
Critical Risks
Next Milestone
Sample Completion
Jun 24 · Daisy
Latest Photos
Manufacturing Timeline · Code Longevity Stack
Sample Stage
Sample Completion
Jun 24Samples ready at factory.
Sample Shipping (Air)
Jun 25 → Jul 9 · 15 daysPackaging design and AI manuscript production occur simultaneously.
Customer Receives Samples
Jul 9Customer evaluation.
Sample Approval & Deposit Payment
Jul 12Depends on: Required before production starts.
Production Stage
Production Starts
Jul 13Depends on: Deposit received · Artwork approved
Inner Bag Production
Jul 13 → Jul 25 · 13 daysRuns parallel with outer box production.
Outer Box Production
Jul 13 → Jul 20 · 8 daysRuns parallel with inner bag production.
Final Assembly & Filling
Jul 26 → Aug 1 · 7 daysRequires completion of bags and cartons.
Production Completed
Aug 2Total manufacturing time: 20 days.
Shipping Stage
Vessel Departure
Aug 3–5Sea Freight Transit
Aug 5 → Sep 9 · 25–35 daysEstimated arrival Aug 28 – Sep 9.
Destination Port Arrival
Aug 28 – Sep 9Customs Clearance
· 2–7 daysTrucking to Warehouse
· 2–5 daysInventory Received
Tip: click any status pill to cycle Pending → In Progress → Completed → Delayed → Critical.